🧱 Estimate the roof slab: concrete, cement, steel
Civil & MechanicalA house owner asks: "How many cement bags and how much steel for my roof slab?" Estimate it like a site engineer, with M20 concrete (1 : 1.5 : 3).
⭐ Level 1: Trainee0 XP · next level at 300
Concrete volume (wet)6.97 m³
Cement57 bags (50 kg)
Steel (about 80 kg/m³)557 kg
Rough cost (concrete + steel)₹81,520
Dry volume = wet × 1.54 (voids and wastage). Always add 3–5 % for wastage on site.
📘 How it works
Quantity estimation turns drawings into materials and money. Wet volume × 1.54 gives dry volume; split it by the mix ratio, and a 50 kg cement bag is 0.0347 m³.
Volume = area × thickness · Dry = 1.54 × wet · Cement = dry × 1/5.5 ÷ 0.0347 bags · Steel ≈ 80 kg/m³A simplified textbook model for learning. Real designs follow the full codes and standards.