🧵 Balance a garment line to hit the target
Textile & ProductionA T-shirt line has 7 operations. The slowest one sets the output. Put operators where they are needed to hit 100 pieces an hour with the fewest people.
⭐ Level 1: Trainee0 XP · next level at 300
Output per hour✗ 71
BottleneckSleeve attach (0.85 min)
Operators7
Line efficiency✗ 64 %
The bottleneck is Sleeve attach. Add an operator there.
📘 How it works
A line runs at the speed of its slowest operation (the bottleneck). Adding people anywhere else only adds waiting time and lowers efficiency.
Output/hr = 60 ÷ max(SAM ÷ operators) · Efficiency = ΣSAM × output ÷ (operators × 60)A simplified textbook model for learning. Real designs follow the full codes and standards.