📦 Never run out, never overstock
Business & MarketingA wholesale shop keeps running out of a fast-moving item. Set the reorder point with safety stock, and the order size (EOQ), to balance stock-outs against the cost of holding stock.
⭐ Level 1: Trainee0 XP · next level at 300
Order size (EOQ)1,812 units
Safety stock175 units
Reorder when stock falls to1,015 units
Yearly ordering + holding cost₹79,483
Reorder at the reorder point, order the EOQ each time.
📘 How it works
Reorder point = demand during the lead time + safety stock. Safety stock covers variation and grows with the service level and the square root of lead time. EOQ balances ordering costs against holding costs.
EOQ = √(2DS ÷ H) · Safety stock = z·σ·√L · Reorder point = d·L + safety stockA simplified textbook model for learning. Real designs follow the full codes and standards.