📦 Never run out, never overstock

Business & Marketing

A wholesale shop keeps running out of a fast-moving item. Set the reorder point with safety stock, and the order size (EOQ), to balance stock-outs against the cost of holding stock.

⭐ Level 1: Trainee0 XP · next level at 300
🎯 The shop runs out every Saturday. With 99 % in-stock, what is the reorder point? Set the target and keep the yearly cost under ₹1,10,000.
Controls
Results
Order size (EOQ)1,812 units
Safety stock175 units
Reorder when stock falls to1,015 units
Yearly ordering + holding cost₹79,483

Reorder at the reorder point, order the EOQ each time.

📘 How it works

Reorder point = demand during the lead time + safety stock. Safety stock covers variation and grows with the service level and the square root of lead time. EOQ balances ordering costs against holding costs.

EOQ = √(2DS ÷ H) · Safety stock = z·σ·√L · Reorder point = d·L + safety stockA simplified textbook model for learning. Real designs follow the full codes and standards.