Monitoring and earned value
Measuring progress objectively.
๐ Key ideas
- Monitoring compares actual progress with the baseline plan.
- Earned value (EV) is the budgeted value of work actually completed.
- Planned value (PV) is the budgeted value of work scheduled to date; actual cost (AC) is what was spent.
- Schedule variance SV = EV - PV; cost variance CV = EV - AC.
- SPI = EV / PV and CPI = EV / AC; values below 1 indicate delay or overspending.
๐ก Real-life example: Like checking a trip: you planned to cover 200 km by noon, you covered 150 km, and you spent more fuel than expected.
Earned valueBudgeted value of work completed
Planned valueBudgeted value of work scheduled
CPICost performance index EV / AC
SPISchedule performance index EV / PV