Estimating and budgeting

How long and how much.

๐Ÿ“– Key ideas

  1. Estimation methods: expert judgement, analogous (from similar past projects), parametric (rate x quantity) and bottom-up (sum of work packages).
  2. Three-point (PERT) estimate = (optimistic + 4 x most likely + pessimistic) / 6.
  3. The cost baseline is the approved budget over time.
  4. Contingency reserves cover known risks; management reserves cover unknowns.
  5. Track actual cost against budget regularly.
๐Ÿ’ก Real-life example: Like estimating a trip: past trips, distance x fuel cost, and a buffer for traffic.
Analogous estimateEstimate based on similar past projects
Parametric estimateRate times quantity
PERT estimateWeighted average of three estimates
Contingency reserveBudget set aside for known risks