Scheduling and the critical path

Planning tasks over time.

๐Ÿ“– Key ideas

  1. A schedule lists activities, durations, dependencies and dates.
  2. Gantt charts show tasks as bars on a timeline.
  3. The critical path is the longest path of dependent tasks; it sets the minimum project duration.
  4. Tasks on the critical path have zero float (slack); delaying them delays the project.
  5. Milestones mark key events, such as "design approved".
๐Ÿ’ก Real-life example: Like cooking a meal: rice takes 20 minutes and curry 30, but both start together; the curry is on the critical path.
Gantt chartBar chart of tasks over time
Critical pathLongest chain of dependent tasks
FloatTime a task can slip without delaying the project
MilestoneKey event with zero duration