Cost management and earned value

Budgets and performance measurement.

๐Ÿ“– Key ideas

  1. Cost baseline is the approved time-phased budget excluding management reserves.
  2. Contingency reserves cover identified risks; management reserves cover unknown unknowns.
  3. Earned value terms: PV (planned value), EV (earned value), AC (actual cost), BAC (budget at completion).
  4. CV = EV - AC; SV = EV - PV; CPI = EV / AC; SPI = EV / PV.
  5. Forecasts: EAC = BAC / CPI (typical); ETC = EAC - AC; VAC = BAC - EAC.
๐Ÿ’ก Real-life example: Like tracking a home renovation: planned spend, work actually finished and money actually spent.
Earned valueValue of work actually completed
CPICost performance index EV / AC
EACEstimate at completion
Management reserveBudget for unknown unknowns